Electricians finished first floor above ceiling rough-in and continued the second floor rough-in. Low voltage electricians finished pulling wire on the first floor. The HVAC crew continued ductwork on the first floor and refrigeration lines in the attic. CK framers began install of the drywall on the first floor ceilings and continued framing on the second floor. CK carpenters continued window trim installation, door casing install, and began layout of historic newel posts. Painters continued priming and first coat of existing ground floor ceilings. Elevator technicians continued elevator install. Interior masons parged the arches in the bell tower.