Roofers completed removal and installation of new roof sheathing on the main portion of the roof this week, and will continue to install new roof sheathing on the East towers next week. Scaffolding erectors utilized a crane to install beams through bell tower windows to begin tower scaffolding. Masons continued mortar and stone patching around the building. CK laborers removed existing millwork on the
1st and 2nd floor.