Electricians continued second floor wall and ceiling rough-in and poured the generator pad. The HVAC crew continued ductwork on the first floor and refrigeration lines in the attic. CK framers continued installing the drywall on the first-floor ceilings and continued framing on the second floor. CK carpenters continued window trim installation, door casing install, and layout of historic newel posts. Painters continued priming and first coat of existing ground floor ceilings. Elevator technicians continued the elevator install. Flooring crew continued subfloor prep and floor fill on the second floor.