Electricians continued the first floor second floor rough-in and low voltage electricians continued pulling wire on the first floor. The HVAC crew continued ductwork on the first floor and refrigeration lines in the attic. CK framers continued ceilings on the ground and second floor, and framing walls around the elevator shaft. CK carpenters continued window trim installation and door refinishing. Painters continued priming and first coat of existing ground floor ceilings. Scaffolding erecters finished teardown of the exterior scaffold. Elevator technicians began elevator install. Interior masons installed a doorway lintel on the ground floor.