Scaffolders continued installing shoring throughout the courthouse floors. Electricians have started roughing in the interior walls, while HVAC continues layout work on first and second floors. Door and wood restoration on the first floor has begun, and carpenters continued installing stud framing in the ground floor rooms. The plaster crew continued work in the second floor courtroom and has begun patching on the first floor. Interior masons continued lintel installation on the first and ground floors, while exterior masons finished relaying the West gable stones and continued grinding and tuckpointing the clock tower. The concrete crew poured the ground floor courtroom.