CK carpenters have continued wood restoration and installed blocking on the ground floor. The plaster crew has moved on to patching on the ground floor. Painters have started priming existing wood throughout the courthouse. Tuckpointing the clock tower masonry is complete. The demo crew cut remaining walkway openings and has begun brick arch demo for the new egress stair and elevator.