CK carpenters have continued wood restoration on the first floor and installed blocking on the ground floor while the steel crew finished install of structural steel on the clock tower roof. Plaster patching and wood base priming remain ongoing. Exterior masons have now finished washing the clock tower masonry, and interior masons have installed the remaining doorway lintels. Roofers installed roof sheathing and membrane on
the clock tower.