CK carpenters have continued wood restoration on the second floor, with the steel crew installing lateral bracing. Plaster patching and wood base priming remain ongoing. Exterior masons began disassembly of clock tower clock faces. Roofers finished installation of roof sheathing and began work on the copper gutter. The demo crew returned and began floor demo for the elevator and egress stair.