While layout work is still ongoing, HVAC installers began hanging ducting in the attic. CK carpenters continued door and frame restoration on the first floor. CK framers continued installing stud framing on the ground and 1st floor, and the steel crew has installed structural steel on the clock tower roof. Plaster patching on the first floor, lintel installation on the ground and first floor, and clock tower tuckpointing has continued. The demo crew has cut new openings on the ground floor.