Electricians began excavation for the permanent power on the ground floor, with exterior electricians continuing to install lightning protection. The HVAC crew has continued running duct and refrigerant piping on the ground and first floor. CK carpenters and framers have continued wood restoration, framing and drywall installation. The steel crew has continued SOMD and arch steel installation on the second floor. Exterior masons rebuilt the Northwest brick knee wall in the attic, while interior masons finished parge coating on the first floor and began on the second floor. Painters have continued to prime and first coat the first floor of the building.