As we wrap up another week, there has been a flurry of activity throughout the courthouse this week. Securing the electrical conduit for the power coming into the building, wrapping up the steel and masonry work to the Jack arches, continued work to run electrical and low voltage conduit pathways within the building, the final touches on the installation of the steel staircase and handrails, and more windows installed each day. There is so much happening at a quick pace- things look different each day. Hopefully winter turns into spring soon and we can stop filling those propane tank as often.
– Ben Carpenter, Perry County Commissioner
Originally posted to Facebook