Work on the egress stairs has progressed as CK framers continued shaft wall framing and the CK steel crew continued installation. CK concrete crew have poured the water meter room on the ground floor. Interior plumbers continued first floor plumbing rough in. Interior masons continued arch stabilization and arch removal on the first floor. Window installers continued placing windows on the first floor. Insulation installers began spray foaming the attic space. Roofers continued copper downspout install on the West elevation.