Scaffolding on both the East and West sides of the courthouse is 100% complete and is green tagged for use, with tower scaffolding erection to follow after roof sheathing. CK iron workers completed installation of support steel on the north elevation of the attic with the remainder of the attic steel to be delivered onsite on 2/16. Ameritech removed the communication line from West side of building on 2/13. Onsite walkthroughs with potential subcontractors are ongoing.