Scaffolding on the South side of the building remains at 80% complete – the scaffold crew will be back onsite the week of 2/5. The majority of the masonry wall along north elevation in the attic has been rebuilt, and CK iron workers started installation of steel on the North elevation of the attic. Onsite walkthroughs with potential subcontractors are ongoing.