Electricians continued rough-in on second floor and conduit layout for exterior underground power while the HVAC crew built ductwork offsite. CK framers continued shaft wall framing at the egress stair and began ceilings on the second floor. The CK steel crew has finished egress stair installation and arch stabilization. Interior plumbers continued first floor plumbing rough in. Interior masons continued arch stabilization and finished walkway removal on the first floor. Window installers continued placing windows on the ground and first floor. Painters continued priming and first coat of existing door frames on the first floor. Insulation installers have finished spray foaming the attic space. Roofers finished tile and flashing installation and continued copper downspout install on the West elevation.