Electricians continue the rough-in of the second floor and the conduit layout for exterior underground power, with AEP completing set up of the building’s transformer. The HVAC crew has returned to continue ductwork on the first floor and refrigeration lines in the attic. CK framers continued shaft wall framing at the egress stair and continued ceilings on the second floor. CK carpenters continued window trim installation and door refinishing. Interior plumbers continued first floor plumbing rough in. Window installers continued placing windows on the ground and first floor on the West elevation. Painters continued priming and first coat of existing door frames on the first floor. Roofers continued copper downspout install on the North elevation.