Low voltage electrician installed hangers and supports in the attic. The HVAC crew continued running duct on first floor and refrigerant lines in the attic. CK framers continued wall framing and ceilings on the first floor. CK steel crew continued arch stabilization and continued the egress stair. Exterior plumbers tapped the main water line. Interior masons continued arch stabilization and arch removal on the first floor. Window installers continued placing windows on the first floor.