Scaffolding on the South side of the building is 100% complete, with West side scaffolding to be completed by end of next week. CK iron workers completed the majority of the install of support steel on the North Elevation of the attic. Spectrum also removed the overhead fiber line above the West side scaffolding on 2/6. Onsite walkthroughs with potential subcontractors are ongoing.