Electricians continued rough-in on first floor and trench excavation for permanent power while HVAC crew continued running duct on first floor and refrigerant lines in the attic. CK framers continued ceiling and wall framing on the ground floor. The CK steel crew continued SOMD install on the second floor. Exterior masons have finished tuck pointing on the East and South elevations. Roofers have also finished copper flashing, with copper gutter installation still ongoing. Interior masons continued arch stabilization on the first floor and second floor. Painters continued prime and first coat on the ground and first floor.