Electricians continued installing lights and devices on all floors. The HVAC crew continued ductwork and refrigeration lines in the attic. CK framers and carpenters continued wall and ceiling finishing, door hardware installation, and transaction counter casework, and have begun installing exterior doors. Plumbers have continued to install bathroom fixtures and finished the generator tie-in. Painters continued final coats on the ground and first floors, and the faux painter began painting the corridor walls on the first floor. The flooring crew have completed a mockup for the original tile restoration and has begun installing floor fill on the ground floor.