Roofers continued working on the ridge caps on the Northeast and Southeast towers. Exterior masons relayed the South gable. The concrete crew has completed the elevator footer pour and started geofoam installation on ground floor and prepping rebar and elevator shaft wall pour. The plaster crew began removing existing plaster in second floor courtroom. HVAC layout work on the second floor has begun. Lintel installation on second floor and electrical layout work are still ongoing.