Electricians continued installing lights and devices on all floors. The HVAC crew is now working on equipment startup on all floors. CK framers continued access panel and cove ceiling installation. CK carpenters have continued to work on door hardware installation, woodwork for the transaction counter, and exterior door installation. Plumbers have continued to install bathroom fixtures and finished the generator tie-in. Painters continued final coats on the ground and first floors, and the faux painter began painting the corridor walls on the first floor.