Roofers finished the Northeast and Southeast towers, with copper finials to be installed at a later date. Interior masons continued lintel installation on the ground and second floors, while exterior masons relayed the South and East gables and continued grinding joints around the clocktower. The concrete crew poured elevator shaft wall and continued prep for concrete slab pour. Carpenters have continued sanding on the first floor. The plaster crew is now restoring plaster in second floor courtroom. HVAC layout work on first and second floor and electrical layout work on the ground floor are still ongoing.