Electricians continued installing lights and devices on all floors. The HVAC crew continued working on equipment startup on all floors. CK framers continued access panel and cove ceiling installation. CK carpenters have continued to work on door hardware installation and woodwork for the transaction counter, and have begun installing the historic stair’s Newel posts. CK iron workers began installing the handrails of the courthouse’s historic staircase. The sealant crew caulked the ground floor base. Roofers have completed installing TPO on the south roof and are now working on the east. Painters continued final coats on the ground and first floors. Elevator installation is ongoing.