Interior masons continued lintel installation on the second floor, while exterior masons pulled the North gable, West gable, and Southwest corner. The concrete crew poured ground floor rooms. Carpenters continued sanding doors and began framing in the ground floor rooms. HVAC layout work on first and second floor and electrical layout work on the first and ground floor continues, along with plaster restoration in the second-floor courtroom. Painters started mock-up work on the first floor.