Roofers finished painting the clock tower roofing structure and began ridge installation on the Northeast tower as well as box gutters on east and west sides of the courthouse. Masons continued lintel installation on the ground floor and tuckpointing the clocktower. The concrete crew completed the underground tunnel pour and spread footer pour in the ground floor courtroom- preparations for the elevator footer pour have begun. Carpenters continued sanding on the first floor. Electricians began layout work for the courthouse.