Electricians continued installing lights on all floors. The HVAC crew continued ductwork and refrigeration lines in the attic. CK framers and carpenters continued wall and ceiling finishing as well as door hardware installation and began transaction counter casework. Plumbers have continued to install bathroom fixtures and finished the generator tie-in. Painters continued final coats on the ground and first floors, and the faux painter began painting the corridor walls on the first floor. The flooring crew finished laying carpet on the ground, first and second floors.