Scaffolding erectors have installed interior clock tower scaffolding and torn down scaffolding around the tower chimneys. Installation of the clock tower roof, as well as tile installation on the towers has begun. Gutter installation on the North and East side of courthouse is still ongoing. Interior masons have started lintel installation on openings in the ground floor, while exterior masons finished the chimney restoration and continued work on the gables. The concrete crew also continued prep work on the ground floor for the new footer installation.