Scaffolding erectors installed clock tower turret scaffolding and tore down scaffolding inside the historic stairway. Tile installation on the Northeast tower is complete; the roofers have moved on to the Southeast tower. Lintel installation on the ground floor and work on the gables is ongoing. The masons have also begun tuckpointing the clocktower. The concrete crew finishing excavation work for the courthouse’s new elevator pit and egress stair footings. Carpenters began sanding the second floor courtroom in preparation of faux painting.