Electricians have continued installing lights on the ground and first floors. In the attic, the HVAC has continued installing ductwork and refrigeration lines. CK framers and carpenters are still finishing the walls and ceilings on all floors as well as installing door casings and door hardware. Plumbers continued to install bathroom fixtures. Painters are still painting the doors on the ground floor and ceilings on the first floor and second floor. Our faux painter is currently working on the second-floor courtroom’s wood graining. The flooring crew finished laying carpet in the second-floor courtroom.