Roofers finished tile installation on the Southeast tower and have continued work on clock tower roofing structure. Interior masons finished the lintel installation on the ground floor openings and have moved on to the second floor. Work on the gables and tuckpointing the clocktower continues. The concrete crew began foam prep installation and prep for the underground tunnel pour. The carpenters have finished sanding the second floor courtroom and began work on the first floor.