Masons have continued work on stone patching prep, stone patching samples, and stone cleaning samples. Our window supplier is scheduled to be onsite next week to field measure openings. Our roofing contractor is also scheduled to meet onsite next week for a preconstruction meeting, with mobilization expected late next week. Our scaffolding contractor to be onsite next week to install trash chutes for roof demo. CK, our design team, and potential MEP subcontractors met onsite on 2/27 to review scope packages.