Electricians continued the rough-in on the second floor and continued panel wiring for permanent power. HVAC crew continued ductwork on the first and second floor and refrigeration lines in the attic. CK framers continued shaft wall framing at the egress stair and continued ceilings on the second floor. CK carpenters continued window trim installation and door refinishing. Window installers continued window installment and caulking on the North elevation. Painters continued priming and first coat of existing second floor courtroom ceiling. Scaffolding erecters began teardown of the South elevation scaffolding.