Electricians have finished the rough-in of the elevator lights/power and continued the first-floor power rough-in. The HVAC crew continued ductwork on the first and second floor and refrigeration lines in the attic. CK framers continued shaft wall framing at the egress stair and continued ceiling work on the second floor. CK carpenters continued window trim installation and door refinishing. Window installers finished window installment and caulking on the North elevation. Painters continued priming and first coat of the existing second floor courtroom ceiling. Scaffolding erectors finished teardown of the South elevation scaffolding and began the East elevation teardown.

Download PDF