Electricians continued the first floor and panel rough-in while the HVAC crew continued ductwork on the first and refrigeration lines in the attic. CK framers continued shaft wall framing at the Egress stair, ceilings on the second floor, and framing wall around the elevator shaft. CK carpenters continued window trim installation and door refinishing. Window installers finished all elevation window installment. Painters continued their priming and first coat of existing ground floor courtroom ceiling. Scaffolding erectors continued teardown of the East elevation scaffolding. Replicated cast iron newel posts for the historic stair were delivered to the job site.