Electricians continued the rough-in on the second floor and began panel wiring for permanent power. The CK concrete crew poured steel pans for the egress stair. CK framers have continued shaft wall framing at the egress stair and ceiling work on the second floor. CK carpenters continued window trim installation and door refinishing. Interior plumbers finished water meter install, while exterior plumbers have begun installing the storm sewer on North elevation. Window installers began installing windows on the ground and first floor on the North elevation. Painters have continued priming and first coat of existing door frames and walls on the ground and first floor.