Scaffolding erectors completed work on all elevations of the courthouse. Roofers began roof sheathing on clock tower and continued box gutter work on the East towers. Mortar and stone patching around the building and masonry work on the chimneys continues, along with the removal of the existing elevator and plaster ceilings throughout the courthouse. Plumbers began installation of sanitary lines within the ground floor tunnel, with plans to continue ground floor plumbing next week.