Electricians continued second floor wall and ceiling rough-in and have set the generator. The HVAC crew continued ductwork on the first floor and refrigeration lines in the attic. CK concrete installed formwork for the concrete sidewalk on the Southwest side of the building. CK framers continued installing framing and drywall on the second floor. CK carpenters continued door casing on the first and second floor. Painters finished priming the ground floor and are continuing to prime ceilings on the first and second floor. Elevator installation is ongoing. The flooring crew continued floor fill on the first floor and have begun ceramic tiling in the second-floor restroom.