Electricians continued the second-floor wall and ceiling rough-in and exterior work. The HVAC crew continued ductwork on the first floor and installed refrigeration lines in the attic. CK framers and carpenters continued installing framing, drywall, door casing and wood trim on the first and second floors. CK iron workers finished welding the clock tower stairs. Painters continued painting doors on the ground floor and ceilings on the first floor. The flooring crew has begun floor prep on the ground floor. Roofers installed the clock tower’s copper finial and TPO on the south flat roof. The elevator technicians continued installation of the new elevator.