Scaffolding was installed in the main staircase to allow for the demolition of the elevator shaft and second floor plaster ceiling. The demo crew also removed the existing attic staircase Roofers have continued box gutter work on the second tower while the masons removed east gable cap stones- once the underlying brick is restored, the cap stones will be reattached. Masons also continued tuckpointing and chimney restoration. The underground plumbing rough-in on the ground floor is ongoing.