Scaffolding erectors continued work on bell tower scaffolding. Masons continued mortar and stone patching around the building and began masonry work on the chimneys. Installation of sanitary lines on the ground floor has begun. CK iron workers continued the install of steel on the North gable in the attic, with ironworkers to work in tandem with masons for remaining gable work.