Electricians have begun installing lights on the first and second floors. The VAC crew continued ductwork on the first floor and refrigeration lines in the attic. CK framers continued framing install and drywall on the second floor, and carpenters are still working on door casing and wood wainscot in the first-floor courtrooms. The CK concrete crew has finished pouring the new sidewalk. Painters continued painting the doors on the ground floor and ceilings on the first floor. The flooring crew began laying carpet on the ground floor and continued ceramic tiling in the bathrooms. Roofers began TPO on the eastern roof.