CK’s steel crew has installed the remaining support steel in the magistrate courtroom on the first floor and continued steel decking in the attic. Plaster restoration continues on the second floor, and the plaster crew began cutting conduit channels on the second floor. Exterior masons have continued restoration work on the West and North elevation of the building. Interior masons continued the HVAC lintel install and finished the bearing plate install for the new egress stair. The demo crew has removed a wall in the magistrate courtroom and finished demo for the new egress stair.