Electricians have continued roughing-in walls on the ground, first, and second floor and begun installation of lighting protection system. Exterior masons finished clock tower restoration work, reset the North gable cap stones, and continued restoration on the West and North elevations of the building. Interior masons continued HVAC lintel install and grouted the magistrate court pinch beam.