Phase 1 of selective demolition of the ground, first, and second floors was completed, as well as a general demolition cleanup for all three floors.
Selective demolition of the first and second floors continues. Temporary power and lighting was also installed in the courthouse and on-site trailer, and a walkthrough of the building’s clock tower was conducted.
Selective demolition of the first and second floors continues. The building’s built-in furniture demolition is also ongoing.
Selective demolition of the first and second floors continues. The building’s historic radiators were placed in storage, and a temporary power pole was set for the on-site trailer.
Some built-in furniture and the building’s historic radiators were removed as wall protection continues to be installed. The courthouse’s front doors were also moved to the Opera House to await restoration. Demolition of the first and second floors continues.
Cisterns were installed and construction site staging areas were completed. A temporary fence was also installed. Selective demolition at the courthouse is ongoing.
Flooring protections were installed as floor inspections continued. All on-site furniture was also removed from the premises.