Phase 1 of construction is complete. Design Meetings are ongoing. A Future Building Envelope Meeting scheduled for October 23, 2025 will involve masons, scaffolding, roofing, and steel construction
Final demolition cleanup, demolition of the ground floor ramp, and construction of raised wood flooring on the ground floor was completed.
The removal of insulation in the attic was completed, along with demolition of the brick restroom wall all non-historic tiling, and construction of raised wood flooring on the ground floor has begun. Final cleanup of demolition is ongoing.
MEP demolition of the ground, first, and second floors was completed, as well as a general demolition cleanup for the attic. Removal of attic insulation is ongoing.
Phase 1 of selective demolition of the ground, first, and second floors was completed, as well as a general demolition cleanup for all three floors.
Selective demolition of the first and second floors continues. Temporary power and lighting was also installed in the courthouse and on-site trailer, and a walkthrough of the building’s clock tower was conducted.
Selective demolition of the first and second floors continues. The building’s built-in furniture demolition is also ongoing.
Selective demolition of the first and second floors continues. The building’s historic radiators were placed in storage, and a temporary power pole was set for the on-site trailer.
Some built-in furniture and the building’s historic radiators were removed as wall protection continues to be installed. The courthouse’s front doors were also moved to the Opera House to await restoration. Demolition of the first and second floors continues.
Cisterns were installed and construction site staging areas were completed. A temporary fence was also installed. Selective demolition at the courthouse is ongoing.