Phase 1 of construction is complete. Design Meetings are ongoing. A Future Building Envelope Meeting scheduled for October 23, 2025 will involve masons, scaffolding, roofing, and steel construction

Download PDF


Final demolition cleanup, demolition of the ground floor ramp, and construction of raised wood flooring on the ground floor was completed.

Download PDF


The removal of insulation in the attic was completed, along with demolition of the brick restroom wall all non-historic tiling, and construction of raised wood flooring on the ground floor has begun. Final cleanup of demolition is ongoing.

Download PDF


MEP demolition of the ground, first, and second floors was completed, as well as a general demolition cleanup for the attic. Removal of attic insulation is ongoing.

Download PDF


Phase 1 of selective demolition of the ground, first, and second floors was completed, as well as a general demolition cleanup for all three floors.

Download PDF


Selective demolition of the first and second floors continues. Temporary power and lighting was also installed in the courthouse and on-site trailer, and a walkthrough of the building’s clock tower was conducted.

Download PDF


Selective demolition of the first and second floors continues. The building’s built-in furniture demolition is also ongoing.

Download PDF


Selective demolition of the first and second floors continues. The building’s historic radiators were placed in storage, and a temporary power pole was set for the on-site trailer.

Download PDF


Some built-in furniture and the building’s historic radiators were removed as wall protection continues to be installed. The courthouse’s front doors were also moved to the Opera House to await restoration. Demolition of the first and second floors continues.

Download PDF


Cisterns were installed and construction site staging areas were completed. A temporary fence was also installed. Selective demolition at the courthouse is ongoing.

Download PDF