Electricians finished first floor above ceiling rough-in and continued the second floor rough-in. Low voltage electricians finished pulling wire on the first floor. The HVAC crew continued ductwork on the first floor and refrigeration lines in the attic. CK framers began install of the drywall on the first floor ceilings and continued framing on the second floor. CK carpenters continued window trim installation, door casing install, and began layout of historic newel posts. Painters continued priming and first coat of existing ground floor ceilings. Elevator technicians continued elevator install. Interior masons parged the arches in the bell tower.
Electricians continued the first floor second floor rough-in and low voltage electricians continued pulling wire on the first floor. The HVAC crew continued ductwork on the first floor and refrigeration lines in the attic. CK framers continued ceilings on the ground and second floor, and framing walls around the elevator shaft. CK carpenters continued window trim installation and door refinishing. Painters continued priming and first coat of existing ground floor ceilings. Scaffolding erecters finished teardown of the exterior scaffold. Elevator technicians began elevator install. Interior masons installed a doorway lintel on the ground floor.
Electricians continued the first floor and panel rough-in while the HVAC crew continued ductwork on the first and refrigeration lines in the attic. CK framers continued shaft wall framing at the Egress stair, ceilings on the second floor, and framing wall around the elevator shaft. CK carpenters continued window trim installation and door refinishing. Window installers finished all elevation window installment. Painters continued their priming and first coat of existing ground floor courtroom ceiling. Scaffolding erectors continued teardown of the East elevation scaffolding. Replicated cast iron newel posts for the historic stair were delivered to the job site.
Electricians have finished the rough-in of the elevator lights/power and continued the first-floor power rough-in. The HVAC crew continued ductwork on the first and second floor and refrigeration lines in the attic. CK framers continued shaft wall framing at the egress stair and continued ceiling work on the second floor. CK carpenters continued window trim installation and door refinishing. Window installers finished window installment and caulking on the North elevation. Painters continued priming and first coat of the existing second floor courtroom ceiling. Scaffolding erectors finished teardown of the South elevation scaffolding and began the East elevation teardown.
On Wednesday March 19th, The Perry County Board of Commissioners presented 2 mobile AED (Automated External Defibrillator) units to the Village of New Lexington. These units will be deployed with New Lexington Police Officers so they can reduce critical response time during a cardiac arrest. These AEDs are GPS-enabled and are a crucial tool thatRead More…
Electricians continued the rough-in on the second floor and continued panel wiring for permanent power. HVAC crew continued ductwork on the first and second floor and refrigeration lines in the attic. CK framers continued shaft wall framing at the egress stair and continued ceilings on the second floor. CK carpenters continued window trim installation and door refinishing. Window installers continued window installment and caulking on the North elevation. Painters continued priming and first coat of existing second floor courtroom ceiling. Scaffolding erecters began teardown of the South elevation scaffolding.
Electricians continued the rough-in on the second floor and began panel wiring for permanent power. The CK concrete crew poured steel pans for the egress stair. CK framers have continued shaft wall framing at the egress stair and ceiling work on the second floor. CK carpenters continued window trim installation and door refinishing. Interior plumbers finished water meter install, while exterior plumbers have begun installing the storm sewer on North elevation. Window installers began installing windows on the ground and first floor on the North elevation. Painters have continued priming and first coat of existing door frames and walls on the ground and first floor.
March 5, 2025 On Wednesday March 5th, The Perry County Board of Commissioners presented 5 mobile AED (Automated External Defibrillator) units to the Perry County Sheriff’s Department. These units will be deployed with the Perry County road deputies so when they are needed for emergency response they can reduce critical response time during a cardiacRead More…
Northern Perry County Water has CANCELLED the Boil Water Alert for the following areas affected by a water main break: SR 669 SR 345 TWP RD 29 TWP RD 114 TWP RD 154 TWP RD 169 TWP RD 169A Buckeye Valley Rd Butcherknife Rd. Wesley Chapel Rd. All tests received on this date were clear.
March is Developmental Disabilities Awareness Month in the United States. It is a time to raise awareness about developmental disabilities, celebrate the achievements of individuals with these disabilities, and advocate for their inclusion and support.