Electricians continued installing lights and devices on all floors. The HVAC crew continued working on equipment startup on all floors. CK framers continued access panel and cove ceiling installation. CK carpenters have continued to work on door hardware installation and woodwork for the transaction counter, and have begun installing the historic stair’s Newel posts. CK iron workers finished installing the handrails of the courthouse’s historic staircase and began the clock tower ladder installation. Roofers continued installing TPO on the east roof. Painters continued final coats on the ground and first floors. Elevator installation is ongoing.

Download PDF


Electricians continued installing lights and devices on all floors. The HVAC crew continued working on equipment startup on all floors. CK framers continued access panel and cove ceiling installation. CK carpenters have continued to work on door hardware installation and woodwork for the transaction counter, and have begun installing the historic stair’s Newel posts. CK iron workers began installing the handrails of the courthouse’s historic staircase. The sealant crew caulked the ground floor base. Roofers have completed installing TPO on the south roof and are now working on the east. Painters continued final coats on the ground and first floors. Elevator installation is ongoing.

Download PDF


Electricians continued installing lights and devices on all floors. The HVAC crew is now working on equipment startup on all floors. CK framers continued access panel and cove ceiling installation. CK carpenters have continued to work on door hardware installation, woodwork for the transaction counter, and exterior door installation. Plumbers have continued to install bathroom fixtures and finished the generator tie-in. Painters continued final coats on the ground and first floors, and the faux painter began painting the corridor walls on the first floor.

Download PDF


The Perry County Commissioners Ben Carpenter, Scott Owen, and Chase Bennett, proudly recognized the outstanding achievements of the 2025 4-H Still Project award winners on Monday, July 14th. The commissioners expressed their admiration for the hard work and dedication of the young participants, who embody the 4-H motto, “Making the Best Better.”These Rosettes recognize ourRead More…


Electricians continued installing lights and devices on all floors. The HVAC crew continued ductwork and refrigeration lines in the attic. CK framers and carpenters continued wall and ceiling finishing, door hardware installation, and transaction counter casework, and have begun installing exterior doors. Plumbers have continued to install bathroom fixtures and finished the generator tie-in. Painters continued final coats on the ground and first floors, and the faux painter began painting the corridor walls on the first floor. The flooring crew have completed a mockup for the original tile restoration and has begun installing floor fill on the ground floor.

Download PDF


Electricians continued installing lights on all floors. The HVAC crew continued ductwork and refrigeration lines in the attic. CK framers and carpenters continued wall and ceiling finishing as well as door hardware installation and began transaction counter casework. Plumbers have continued to install bathroom fixtures and finished the generator tie-in. Painters continued final coats on the ground and first floors, and the faux painter began painting the corridor walls on the first floor. The flooring crew finished laying carpet on the ground, first and second floors.

Download PDF


Electricians have continued installing lights on the ground and first floors. In the attic, the HVAC has continued installing ductwork and refrigeration lines. CK framers and carpenters are still finishing the walls and ceilings on all floors as well as installing door casings and door hardware. Plumbers continued to install bathroom fixtures. Painters are still painting the doors on the ground floor and ceilings on the first floor and second floor. Our faux painter is currently working on the second-floor courtroom’s wood graining. The flooring crew finished laying carpet in the second-floor courtroom.

Download PDF


  The Perry County Commissioners welcomed the Mid-Ohio Regional Planning Commission (MORPC) to their weekly meeting on May 28th. MORPC is a vital partnership for our County providing resources for planning and infrastructure. Of note we are currently utilizing their summer internship program as we welcome Meredith Seta to our IT department. This program helpsRead More…


Electricians continued installing lights on the first and second floors and wells as exterior work. The HVAC crew continued ductwork on the first floor and installation of refrigeration lines in the attic. CK framers continued to install framing and drywall on the second floor, while CK carpenters continued door casing and began installing door hardware. Graves lumber carpenters installed the intermediate tower stair platform. Plumbers continued to install bathroom fixtures. The CK concrete crew poured the Northwest sidewalk. Painters continued painting the doors on the ground floor and ceilings on the first and second floor. Plasterers installed the eagle medallion in the first-floor corridor. The flooring crew began laying carpet in the first-floor courtrooms. Roofers continued TPO on the Eastern roof.

Download PDF


From Left to Right: Perry County Commissioner Scott Owen, State Rep. Jodi Salvo, Congressman Troy Balderson, Muskingum County Commissioner Melisa Bell, Perry County Commissioner Chase Bennett, Tuscarawas County Commissioner Kristin Zemis. WASHINGTON, D.C. – Perry County Commissioners Scott Owen, and Chase Bennett joined more than 60 county leaders from across Ohio in Washington this weekRead More…