September 26, 2025 | Perry County Courthouse Weekly Summary
Electricians continued installing lights and devices on all floors. The HVAC crew continued working on equipment startup on all floors. CK framers continued access panel and cove ceiling installation. CK carpenters have continued to work on door hardware installation and woodwork for the transaction counter, and have begun installing the historic stair’s Newel posts. CK iron workers finished installing the handrails of the courthouse’s historic staircase and began the clock tower ladder installation. Roofers continued installing TPO on the east roof. Painters continued final coats on the ground and first floors. Elevator installation is ongoing.