CK’s steel crew began lateral steel install on the second floor, while the exterior masons finished disassembly of clock tower clock faces. Demolition of the 2nd floor ceiling jack arch has begun. The plumbing ground floor rough in remains ongoing, but installation of first floor in-wall plumbing has begun.