The HVAC crew installed above ceiling units and continued duct layout. The CK steel crew has begun the lateral steel install on the second floor. The plaster crew finished creating the eagle medallion mold for the first-floor corridor. Priming is now complete- painters began their first coat in the second-floor courtroom. Reassembly of clock tower clock faces has begun, and the elevator shaft erection is complete. Roofers finished roof tile and copper gutter installation on the clock tower, with TPO roof in the bell tower expected to finish early next week. Plumbing installation of the first and ground floors continues.